DUE TO ONGOING CONSTRUCTION WORK ON THE ACCESS DRIVEWAY, THE SHED WILL BE CLOSED ON MONDAY 18th JUNE 2012.
THIS WORK MAY OR MAY NOT BE COMPLETED BY THE END OF THE WEEK. IF NOT COMPLETED, THE SHED WILL ALSO BE CLOSED ON FRIDAY 24TH JUNE 2012.
PLEASE RING 0466266083 ON FRIDAY 24 th JUNE FOR FURTHER DETAILS.
JOHN W
Friday, June 15, 2012
Friday, May 18, 2012
SHED REOPENING MONDAY 21st MAY 2012
GOSFORD COMMUNITY MENS SHED WILL REOPEN ON MONDAY 21st MAY 2012.
AT THIS STAGE ONLY HALF OF THE DRIVEWAY HAS BEEN CONCRETED.
THERE IS STILL NO MOTOR VEHICLE ACCESS OR PARKING AVAILABLE.
ACCESS TO THE SHED IS VIA A PATHWAY ALONGSIDE THE CONSTRUCTION SITE. THANK YOU FOR YOUR SUPPORT AND UNDERSTANDING OVER THE PAST 4 MONTHS.
SEE YOU IN THE SHED.
JOHN W.
AT THIS STAGE ONLY HALF OF THE DRIVEWAY HAS BEEN CONCRETED.
THERE IS STILL NO MOTOR VEHICLE ACCESS OR PARKING AVAILABLE.
ACCESS TO THE SHED IS VIA A PATHWAY ALONGSIDE THE CONSTRUCTION SITE. THANK YOU FOR YOUR SUPPORT AND UNDERSTANDING OVER THE PAST 4 MONTHS.
SEE YOU IN THE SHED.
JOHN W.
Sunday, May 6, 2012
SHED CLOSED MONDAY 7th May 2012
DUE TO INABILITY TO REMOVE ALL OF THE ASBESTOS ON FRIDAY, WE ARE UNABLE TO ACCESS THE SHED AGAIN ON MONDAY 7th MAY 2012.
John W
John W
Wednesday, May 2, 2012
NO ACCESS TO SHED
DUE TO THE REMOVAL OF ASBESTOS IN THE BUILDING WORKS IN PROGRESS, THE SHED WILL BE CLOSED ON FRIDAY 4th MAY 2012.
John W
John W
Friday, April 27, 2012
SHED UPDATE
Work on the Front Building is progressing slowly.
We still have no vehicle access which means that those with disabilities are unable to traverse the pathway down to the shed. Despite this inconvenience, a number of members are still turning up on Mondays and Fridays . When the new driveway has been poured and we have full access once again, I will advise via this Blog. Watch this space.
Regards
John W.
We still have no vehicle access which means that those with disabilities are unable to traverse the pathway down to the shed. Despite this inconvenience, a number of members are still turning up on Mondays and Fridays . When the new driveway has been poured and we have full access once again, I will advise via this Blog. Watch this space.
Regards
John W.
Sunday, March 18, 2012
SHED UPDATE
SHED WILL BE OPEN MONDAY 19/3/12.FROM 7AM TO 1PM.
THERE WILL BE NO MOTOR VEHICLE ACCESS.
ACCESS BY WALKING DOWN THE PATHWAY TO THE REAR OF THE BUILDING.
ANY QUERIES PHONE 0466266083.
John W
THERE WILL BE NO MOTOR VEHICLE ACCESS.
ACCESS BY WALKING DOWN THE PATHWAY TO THE REAR OF THE BUILDING.
ANY QUERIES PHONE 0466266083.
John W
Thursday, March 8, 2012
TEMPORARY CLOSURE UPDATE
DUE TO WET WEATHER THE BUILDERS HAVE BEEN PUT BACK 1 WEEK.
WE ARE UNABLE TO ACCESS THE SHED UNTIL MONDAY 19TH MARCH 2012.